New Building Project Construction Updates
Posted on June 2, 2023
Welcome to the Clinic for Special Children’s new building project updates page! We will be posting construction updates frequently and feature drone site videos and time-lapse videos. For more information on the new building project or to donate, please visit www.clinicforspecialchildren.org/campaign.
June 5, 2023
What a difference two weeks has made! Today on the site crews were setting the structural steel for the main floor of the building and installing decking on the main floor. All steel should be completed by the end of this week! The crew will also focus on preparation for framing this week. Weather permitting, next week should consist of installing all decking on each floor, preparations to pour concrete on top of the decking, backfilling dirt to the poured wall foundation, and trenching for electrical service.
Enjoy the time-lapse videos below from May 30 to June 5th (both the front and back of the building) and a site footage drone video from today.
Key construction dates coming up:
- Week of 6/12 – installing decking, prepare to pour concrete on top of decking, backfilling dirt to the foundation, trenching for electrical service
- Week of 6/19 – pouring concrete for the first and second floors
- Week of 6/26 – setting heavy timbers on the second floor and framing the basement and first floors
- Week of 7/3 – exterior sheeting to begin
- Week of 7/10 – trusses to be set
Site Footage Video | June 5, 2023
Time Lapse Video | Front of Building | May 30 – June 5
Time Lapse Video | Back of Building | May 30 – June 5
May 23, 2023
The basement concrete floor has been poured and set! An area that was just dirt a few weeks ago now holds a solid foundation. We’re looking forward to seeing the steel erected in the next few weeks. We have installed a new time-lapse video in the front of the building to capture the progress that will now be visible from the front.
Enjoy the time-lapse videos below from May 16 – May 23 (both the front and back of the building) and a site footage drone video from today.
Key construction date coming up:
- Week of 5/29 – the building will start to take shape! Steel will begin to be erected and will take about 3 weeks to finish.
Site Footage Video | May 23, 2023
Time Lapse Video | Front of Building | May 16 – May 23
Time Lapse Video |Back of Building | May 16 – May 23
May 16, 2023
The past week has seen a lot of progress – most notably, the finishing of the back wall and the laying of stone in the basement. Enjoy a time-lapse video below from May 9 – May 16 and a site footage drone video from today.
Key construction dates coming up:
- Week of 5/22 – the basement concrete floor will be poured
- Week of 5/29 – the building will start to take shape! Steel will begin to be erected and will take about 3 weeks to finish.
Site Footage Video | May 16, 2023
Time Lapse Video | May 9 – May 16
May 9, 2023
So much progress has been made in the past several weeks! The back cinder block wall is almost complete and pipes have been laid throughout the building footprint. Enjoy a time-lapse video below from April 25 – May 9 and a site footage drone video from today.
Some key construction dates coming up:
- Week of 5/15 – stone will be laid in the basement to prepare for concrete to be poured
- Week of 5/22 – the basement concrete floor will be poured
- Week of 5/29 – the building will start to take shape! Steel will begin to be erected and will take about 3 weeks to finish.
Site Footage Video | May 9, 2023
Time Lapse Video | April 25 – May 9
April 25, 2023
If you happen to pass by the construction site, you’ll notice that you can now see large towers from a distance! In the past two weeks, both stairwells and the elevator shaft have taken shape. It’s exciting to see recognizable elements of the building being constructed – crossing our fingers for great weather this Spring and optimal conditions for construction.
Site Footage Video | April 25, 2023